Lack of preparation behind slow disbursement of public funds: Deputy PM

Last year, Vietnam’s disbursed amount of public funds stood at 77.3% of the year’s estimate, lower than in the same period of the previous year when 82.66% of the year’s allocations were disbursed.

Slow disbursement of public funds has been a persistent issue for many years, for which a lack of preparation from the investment procedures to site clearance has been one of the main issues.

 Deputy Prime Minister Le Minh Khai at the discussion. Source: quochoi.vn

Deputy Prime Minister Le Minh Khai gave the remarks at a discussion session held by the Standing Committee of the National Assembly (NA) on public investment in the 2021-2025 period today [January 19].

Last year, Vietnam’s disbursed amount of public funds stood at 77.3% of the year’s estimate, 6% lower than that of the same period last year. Upon breaking down, the disbursement of domestic funds reached 84% of the plan, and that of foreign sources hit just 26.77%.

Statistics from the Ministry of Finance (MoF) revealed only 20 out of 63 provinces/cities and seven ministries have spent over 80% of their budget allocations, while 30 from the total 50 ministries/ministerial level-agencies and 16 provinces/cities recorded the figure below 65%.

For 2022 and the subsequent years, Khai said the Government is committed to ensuring flexible management of both mid-term public investment funds and the economic recovery program.

“Each project under the mid-term public investment plan and the recovery program would be reported to the Standing Committee for greater efficiency in disbursement,” Khai noted.

On this issue, Deputy Auditor General Nguyen Tuan Anh urged the Government to take drastic action to improve the disbursement rate, including a clear deadline for completion with severe penalties for those failing to meet it.

NA Chairman Vuong Dinh Hue noted a key factor for efficient state budget allocation is thorough preparation in the pre-investment process.

A Government report suggested it plans to allocate VND824.7 trillion ($36.3 billion) in mid-term public investment plan 2021-2025 for ministries, ministerial-level agencies, and localities.

So far, nearly VND640 trillion ($28.2 billion) is subject to the Standing Committee’s approval before being allocated for disbursement.

Vice Minister of Planning and Investment Tran Quoc Phuong said the ministry is prepared to speed up investment procedures for public projects to avoid possible delay, as well as take steps to supervise the implementation process.

As of December 27, 2021, Hanoi disbursed a total of VND25.38 trillion ($1.11 billion) of public funds, equivalent to 61% of the target set by Prime Minister Pham Minh Chinh.

Reactions:
Share:
Trending
Most Viewed
Related news
Hanoi apartment market heads for major supply surge beginning in 2026

Hanoi apartment market heads for major supply surge beginning in 2026

Hanoi’s apartment market is entering a new growth phase with a strong supply wave expected from 2026 as major projects launch across all segments from social housing to high-end developments.

Two social housing projects offered for sale as Hanoi strives to meet mounting demand

Two social housing projects offered for sale as Hanoi strives to meet mounting demand

Hanoi launches sales for CT-05 and CT-06 social housing projects in Quang Minh Commune, offering low-cost units as the city faces rising housing pressure.

Vietnam creates National Housing Development Fund to boost social housing supply by 2030

Vietnam creates National Housing Development Fund to boost social housing supply by 2030

Vietnam has taken a major step toward expanding affordable housing by establishing the National Housing Development Fund, a new financial mechanism designed to accelerate social housing development and stabilize the property market.

Hanoi to see sharp jump in land prices under new 2026 pricing framework

Hanoi to see sharp jump in land prices under new 2026 pricing framework

The sharp increases raise concerns over affordability, investment risks and shifting market behavior as land values climb across diverse areas of the city.

Hanoi to launch $34 million canal project to curb flooding, revive To Lich River

Hanoi to launch $34 million canal project to curb flooding, revive To Lich River

Hanoi starts a $34-million project to upgrade Thuy Phuong Canal, improve drainage and restore To Lich River flow with completion expected by Q3/2026.

Hanoi greenlights sub-zone B of 16,000-hectare southern sports and housing project

Hanoi greenlights sub-zone B of 16,000-hectare southern sports and housing project

The sub-zone B is designed to be a complex containing sports facilities, housing, public services, schools and agricultural land, with an estimated accommodation of 250,000–285,000 residents.

Strong public participation to drive Hanoi’s sustainable and dynamic urban growth

Strong public participation to drive Hanoi’s sustainable and dynamic urban growth

Hanoi’s development depends on effective planning, mobilization of social resources and clear decentralization with accountability and transparency.

Hanoi housing prices surge sharply in Q3/2025 amid limited supply

Hanoi housing prices surge sharply in Q3/2025 amid limited supply

Hanoi apartment prices remained high in Q3/2025, rising sharply amid limited supply and growing affordability concerns.