ODA disbursement hits 19% of target in Jan-Sep

The Covid-19 pandemic has significantly impacted the construction progress of public projects across the country.

Despite the strong efforts from government agencies, the disbursement rate of ODA (official development assistance) projects in the first nine months of 2021 stood at 19.03% of the plan.

 An overpass at the intersection of Nguyen Van Huyen and Hoang Quoc Viet street in Hanoi. Photo: Thanh Hai

Director of the Department of Debt Management and External Finance under the Ministry of Finance (MoF) Truong Hung Long said at an online conference held today [October 7].

According to Long, seven ministries and ministerial-level agencies reported a 0% disbursement rate, while nine others requested to return their entire allocated funds of VND8 trillion ($352.3 million), or 44.08% of total ODA funds this year.

“Such an amount may be transferred to agencies or localities in need of capital, or return to the central budget if no request arises,” Long said, while acknowledging it is unlikely to realize the goal of disbursing over 95% of the ODA funds this year.

Vice Director of the Department of Debt Management and External Finance Vo Huu Hien added this year, the Government allocated a total of VND51.5 trillion ($2.26 billion) in ODA funds, in which VND16.63 trillion ($732.5 million) went to ministries and VND35 trillion ($1.54 billion) to local governments.

Hien pointed out the serious Covid-19 situation in 19 provinces/cities, including major cities of Ho Chi Minh City, Hanoi, and Danang, which has directly impacted economic activities and the progress of public projects, forcing many to temporarily stop or preventing foreign consultants from entering Vietnam.

Other issues have also contributed to the delay in the construction progress, including the difficulties in site clearance, resettlement of affected households, slow progress in bidding procedures, or adjustment to financing agreement, Hien continued.

Hien called for greater efforts to accelerate the disbursement of ODA funds in areas with a low risk of infection to compensate for the delayed works at locations under lockdown.

The MoF, for its part, would closely cooperate with other agencies in speeding up the disbursement of public funds, including the ODA and preferential loans, Hien stressed.

Hien called for project owners to enhance efficiency in managing ODA projects and report any difficulties to competent authorities for timely address.

“It is essential for project owners to select qualified and capable consultants in project design to avoid potential modification in the execution,” he said.

In a recent meeting in early October, Deputy Prime Minister Pham Binh Minh suggested the Vietnamese Government is in process of drafting a new decree in replacement of decree No.56 on ODA management, with a view to both simplify the administrative process and ensure efficiency in the use of ODA.

Hanoi is among the cities that were hit hard by the fourth Covid-19 outbreak. The city, however, still posted a positive disbursed amount of ODA funds at VND3.66 trillion ($161 million) in the first nine months of 2021, or 46.7% of the yearly target and up 7.2% year on year.

The rate was significantly higher than that of the national average and showcased strong efforts from local authorities to speed up economic recovery, with public investment seen as a major solution to boost growth during the pandemic.

Reactions:
Share:
Trending
Most Viewed
Related news
Hanoi plans major incentives to expand social housing supply by 2030

Hanoi plans major incentives to expand social housing supply by 2030

The draft regulation may pull down construction costs for social housing developers, dragging the prices down to meet demand from low-income earners.

Hanoi approves new social housing project in suburban Hoai Duc Commune

Hanoi approves new social housing project in suburban Hoai Duc Commune

Hanoi has greenlit a new social housing project in Hoai Duc Commune, set to provide homes for more than 2,000 residents as part of the city’s wider development plan.

Push for early implementation of Ninh Thuan nuclear power projects

Push for early implementation of Ninh Thuan nuclear power projects

Both plants are required to begin operations during the 2030–2035 period.

Prime Minister agrees to raise income thresholds for housing

Prime Minister agrees to raise income thresholds for housing

The prime minister urged provinces and cities to increase supply, replicate effective models, and ease financing conditions for developers and homebuyers to reach the target of 100,000 units in 2025.

Hanoi starts housing project for public security force

Hanoi starts housing project for public security force

The project will provide more housing supplies for public security forces and help Hanoi fulfill its housing development this year.

Hanoi lifts barriers to social housing access

Hanoi lifts barriers to social housing access

Expanding access for informal workers would allow developers to sell or lease the available stock more quickly, avoiding waste.

Vietnam to invest US$915-million expressway to smooth connection with Laos  

Vietnam to invest US$915-million expressway to smooth connection with Laos  

This key transport project will promote Nghe An’s socio-economic development and strengthen Vietnam’s connection with Laos.

Gia Binh Airport – Hanoi link named national key project

Gia Binh Airport – Hanoi link named national key project

The planned Gia Binh Airport–Hanoi road will be 35 km long and 120 m wide, with a total investment of VND71.150 trillion (US$2.8 billion).