Log in
Property

PM wants to finish 500kV transmission line by Independence Day

This project has a transmission capacity of around 2,400 MW and will enhance electricity supply to the northern region from 2025.

Prime Minister Pham Minh Chinh has set the goal of completing the 500 kV Circuit 3 project before September 2, with the inauguration scheduled for this year's Independence Day.

 Overview of the meeting. Photo: Nhat Bac

Chinh fixed the target during an online meeting on August 13 with the provinces of Ha Tinh and Nghe An regarding the 500 kV Circuit 3 project, specifically the Quang Trach to Pho Noi section.

The 500 kV Circuit 3, which consists of four component projects, spans a total length of 514 km, connecting Quang Trach in the central province of Quang Binh to Pho Noi in the northern province of Hung Yen. The total investment for this project is approximately VND23 trillion (US$1 billion). Construction of the component projects commenced at the end of last year and the beginning of this year.

According to Chinh, this project has a transmission capacity of around 2,400 MW and will enhance the electricity supply to the northern region from 2025.

He urged agencies and localities to "be determined and put in more effort during this final sprint." The objective is to complete the project before September 2 and inaugurate it on Independence Day (September 2).

 The 500kV Lin3 -Circuit 3 project. Photo: EVN

In an earlier report, EVN Chairman Dang Hoang An stated that the group aims to have the entire project operational by  August 25. The 500 kV Nam Dinh 1 – Thanh Hoa component project was launched on June 30. Resources are being concentrated on the remaining three projects to meet the deadline. The Nam Dinh I – Pho Noi and Quynh Luu – Thanh Hoa projects are expected to be commissioned before August 19, while the Quang Trach – Quynh Luu project is set to be up and running before August 31.

To ensure progress, Chinh has instructed all parties to review, assign tasks in detail, and work continuously around the clock. Specifically, he has tasked the Ministry of Industry and Trade with regular inspections and supervision to promptly resolve issues and conduct acceptance tests. The Ministry of Defense has been directed to coordinate with EVN to review and mobilize machinery, equipment, and labor support for construction.

The Ministry of Agriculture and Rural Development is responsible for guiding the change in forest land use. At the same time, the Ministry of Natural Resources and Environment will provide environmental guidance to ensure restoration upon project completion. The Ministry of Internal Affairs, relevant ministries, and local authorities are tasked with proposing appropriate remuneration at all levels for those involved in the project.

The 500 kV Line-Circuit 3 Project comprises four component projects with a total length of nearly 520 km and involving 1,179 tower foundations. The overall investment is about VND23 trillion ($1 billion). This project covers 211 communes and wards across 43 districts and towns in nine provinces: Quang Binh, Ha Tinh, Nghe An, Thanh Hoa, Ninh Binh, Nam Dinh, Thai Binh, Hai Duong, and Hung Yen.

This initiative is essential for linking inter-regional power grids and enhancing electricity supply to the northern region. The 500 kV Quang Trach-Pho Noi transmission line will boost capacity from 2,200 MW to roughly 5,000 MW, enabling the transfer of power from both thermal and renewable energy sources in the North Central region to the national grid. Additionally, it will help reduce the load on existing 500 kV lines and prevent overloading.

Reactions:
Share:
Trending
Most Viewed
Related news
Vietnamese Government set to revise Land Law 2024

Vietnamese Government set to revise Land Law 2024

Land legislation still presents shortcomings and remains inconsistent with the two-tier local government model and the country’s development objectives in the new era.

Hanoi approves 150 land sites for commercial housing projects

Hanoi approves 150 land sites for commercial housing projects

Hanoi plans to use 150 land areas to build commercial housing infrastructure and increase the supply of affordable homes.

Nearly 22,000 new homes in Hanoi listed in H1

Nearly 22,000 new homes in Hanoi listed in H1

Apartments made up the majority of housing units available for sale in Hanoi during the first half of 2025.

Hanoi to allocate 720ha of land for commercial housing projects

Hanoi to allocate 720ha of land for commercial housing projects

The capital authorities target to use available land resources to build more affordable homes, thus increasing the supplies for the real estate market.

Interest rates for young homebuyers capped at 5.9% per annum

Interest rates for young homebuyers capped at 5.9% per annum

The new rule about how much interest can be charged is expected to make it easier for young people to buy houses in big cities in Vietnam.

Market manipulation concerns follow Vietnam's land pricing deregulation

Market manipulation concerns follow Vietnam's land pricing deregulation

While removing land pricing rules will positively impact Vietnam's real estate market, local authorities should be aware of attempts to manipulate market prices.

National Assembly ratifies int’l financial center project

National Assembly ratifies int’l financial center project

The financial center is expected to be among the world’s top 75 by 2035 and in the top 20 by 2045.

Vietnam to finalize nuclear power plant deal with Russia in July

Vietnam to finalize nuclear power plant deal with Russia in July

Vietnam resumes its nuclear power program and complete within five years.